Digital infrastructure · Dresden area, Germany · 2025

Data-center site · Dresden area

Preliminary assessment and structuring of information for a potential data-center site, bringing property, planning and power-supply questions together for further project evaluation.

Reported grid connection capacity
120 MWFigure stated in the April 2025 project brief; not a confirmed grid connection commitment.
Project stage
Preliminary site reviewAssessment of site and development conditions.
Technical topics
Grid connection · Heat reuse · Backup supplyQuestions concerning the interaction of supply infrastructure.

Organising site information

The project description for the Dresden-area site stated grid connection capacity of 120 MW. The assessment needed to relate this scale to the property, planning position and supporting infrastructure. A central task was to organise the available information and identify the additional details required for a further decision.

Grid, power supply and heat

The technical questions covered the connection point, voltage level, the terms of possible grid agreements and additional network costs. Backup power, batteries and potential use of waste heat by nearby consumers were also considered.

Planning and development conditions

Further questions concerned plot boundaries, site infrastructure, planning status, fire safety, potential contamination and expansion land. The work brought these topics together in a question list and concise project profile, providing a basis for further technical and financial clarification with the parties involved.

Preliminary site review in April 2025 based on the project information available at the time. Grid connection capacity is distinct from usable IT capacity.