Digital infrastructure & energy · Brandenburg an der Havel, Germany · 2026 · ongoing

Generaldepot Havel · Data-center and energy concept

For this existing industrial site, DMS Development prepared an investment memorandum assessing data-center use, power supply and phased development. The concept is now being developed further, with site requirements and investor interest under review.

Site area
approx. 13.35 ha
Existing hall space
approx. 59,000 m²
Power supply scenario
50–100 MW electricalInitial electrical supply scenario under assessment

From industrial site to campus concept

The concept examines how the existing halls and open land could accommodate a modular data-center and energy campus. Building configuration, space requirements and the planning framework are considered alongside a coordinated sequence of development phases.

Power supply and development phases

A central part of the work compares grid connection with on-site gas-fired power generation. For an initial development stage, the concept considers 50–100 MW of electrical supply, subject to technical assessment of grid connection and potential on-site generation. The concept coordinates the timing and technical requirements of power supply with each development phase.

Investment memorandum and economic assessment

The financial assessment links site and land-use options with power and space scenarios. Capital requirements, development phases and transaction structure provide the basis for investor discussions and subsequent technical and financial assessment.

Concept development and investor engagement are ongoing. Energy supply, technical design and permitting feasibility remain under assessment.

Contact

To discuss this area of work or a project of your own.